Jobbers progress billing function is great for this. My advice is to make sure that the progress bench marks are clear. For example: DON'T do - XX amount when job is 50% done. What is 50%?
Instead do it like this - XX amount when wiring laid out, XX when boxes are tested etc (sorry I don't know what your bench marks would be on a larger project). You get my drift.
For us we'll do
Bench mark 1 - Demo completed
bench Mark 2- Rough in complete (then define that)
bench mark 3- Tile installed and grouted
Bench mark 4 - Vanity installed and tested
bench mark 5 - final walk through
etc etc. Basically make is crystal clear what that bench mark looks like and you'll never have anyone question it. If you use the jobber function, have a line item that describes what done is.